盾构超近距离上跨既有线技术研究
A Study of the Technique for a Shield to Under-Cross an Existing Railway at an Extra-Short Distance
  
中文关键词:盾构掘进  临时竖井  注浆加固  施工监测
英文关键词:drilling with a shield  temporary shaft  slip-casting for consolidation  construction monitoring
基金项目:
作者单位
韩鹄 中铁十八局集团第五工程有限公司天津300450 
摘要点击次数: 367
全文下载次数: 142
中文摘要:
      地铁盾构超近距离上跨既有线施工,如何保证盾构正常施工及既有线的结构安全及正常运营,是施工中的关键点。结合沈阳地铁十号线中松区间超近距离上跨既有二号线工程,采取利用临时竖井进行障碍物的清除、通过深孔注浆对既有线两侧的土体进行加固、既有线内部施作临时支顶系统、对既有隧道进行实时监测、盾构施工过程中严格控制掘进参数等措施,确保了既有线的安全,为类似地铁施工提供了借鉴和参考。
英文摘要:
      When a subway shield is used to perform the drilling construction over an existing railway at an extra short distance,how to ensure the normal operation of the shield,and the structural safety and the normal operation of the existing railway are the key points of the construction. With the Zhongsong Section of the project of Subway Line 10 in Shenyang,which under-crosses the existing railway of Line 2 at an extra short distance,as the engineering background,dealt with in the paper are the construction techniques adopted for the project, which include adopting temporary shafts for the removal of obstacles, consolidating the earth bodies on both sides of the existing railway by means of the deep-hole slip casting,providing temporary internal top supporting system for the existing railway,performing timely monitoring of the existing tunnel, strictly controlling the drilling parameters in the course of the shield drilling and other necessary measures.Because of the adoption of all those measures,the safety of the existing railway is fully ensured.The paper may serve as a useful reference for the construction of other similar subways.
韩鹄.盾构超近距离上跨既有线技术研究[J].国防交通工程与技术,2018,16(1):54~57