TSP及TEM结合法在隧道超前地质预报中的应用 |
The Application of the TSP TEM Combined Method to the Advanced Geological Prediction During Tunnel Construction |
|
中文关键词:岩溶隧道 超前地质预报 TSP法 瞬变电磁法(TEM) |
英文关键词:karst tunnel advanced geological prediction Tunnel Seismic Prediction(TSP) Method Transient Electromagnetic Method(TEM) |
基金项目: |
|
摘要点击次数: 98 |
全文下载次数: 44 |
中文摘要: |
隧道超前地质预报的方法有多种,但每种方法都有一定的不足,单一的预报方法难以得到满意的结果。为提高预报精度,基于开挖面揭示围岩情况,在紫云隧道地质超前预报中采用TSP与瞬变电磁法相结合的方法准确预报了开挖面前方富水地质体的存在。工程实践表明,采用多种手段相互印证的方法,可以有效提高预报结果的准确性,从而指导隧道安全施工。 |
英文摘要: |
There are various methods to predict tunnel geology in advance, but each of the methods adopted has certain shortcomings. It is difficult to achieve satisfactory results by means of a single forecasting method. In order to improve the prediction accuracy, the TSP TEM Combined Method is applied to accurately predict the existence of water rich geological bodies in front of the excavation face of the Ziyun Tunnel upon the basis of the revelation of the surrounding rock conditions by the work face. Engineering practice shows that the method of mutual verification by multiple means can effectively improve the accuracy of the prediction results and guide the safe construction of tunnels. |
菅永明.TSP及TEM结合法在隧道超前地质预报中的应用[J].国防交通工程与技术,2021,19(1):76~79 |